Weekly Update (10/24/16 – 10/29/16)

Have you seen the progress between 6th and 8th streets? All concrete work, including the west side of Main Street, has already been completed and it looks fantastic!

Traffic has switched lanes to the south side of Main Street between 6th and 8th streets and concrete removal will be taking place this week on the south side of Main Street between 6th and 7th streets.

Next week, milling will be taking place on Main Street between 4th and 6th streets. During this time, parking will be restricted.

Look out for tree installation this Friday and Saturday!

Please know that even though October is the last month for property owners meetings, you can still reach out to us at any time with questions or concerns. We will still continue to raise awareness around the Main Street Streetscapes Project until it has been completed.