Weekly Update (4/4/16-4/8/16)

As another week starts off, progress is being made on both ends of Main Street.

As you can see below, while ramps were temporarily moved last week crews were able to install curbs in the upper Main Street Section–located between 10th and 11th Street on the north side–preparing for paver bands and sidewalk installation this week.

10-11 curbs3.29         10-11 curbs2.3.29

In Phase 1–south side of Main Street between 4th and 5th Street–the curbs, sidewalks and asphalt were all removed last week. This week crews will  be excavating tree wells and begin preparing for the installation of the curb in this section.

To stay current on everything that is happening with the Main Street Streetscape renovation project, sign-up for notifications under the News page!