Weekly Update 5/26/20

Progress is coming along for Phase 3 of the Streetscape Project.  In the past few weeks, construction continues with the installation of the storm water system throughout the 10th and Main Street areas. Duke Energy also installed a new service pole. This week (May 26th-29th) will see the completion of the installation of the storm water system throughout the entire Phase 3 project (weather pending).  Crews will also begin the removal process of sidewalk and curb along North 10th Street from Ferry to Main Street toward the end of the week. They will also be installing temporary access points to the businesses and residents along North 10th Street once the sidewalk is removed. They will be installing stone approaches with safety precautions put in place.