Weekly Update 6/16/20

Phase 3 of the Streetscapes project for Downtown Lafayette continues to develop as crews finished installing the storm water system with an additional safety check last week (June 8 – 12th). Crews also finished the removal of old sidewalk, curb, and drive along N. 10th St. from Ferry St. to Main St., allowing for mobilization for concrete work! This coming week, (June 15 – 19th) concrete crews will continue to hand form and pour the curb and gutter along N. 10th St. from Ferry St. to Main St. Once this step is complete, drive approaches will begin followed by framing processes for the sidewalk.