Weekly Update 6/23/20

Developments continue for Phase 3 of the Streetscapes project for Downtown Lafayette. Huston Electric was onsite to install and pour the lighting foundations on N. 10th St. as well as finishing the installation of the electrical conduit for streetlights last week (June 15 – 19). The concrete crew also finished the straight sections of the curb and gutter along N. 10th St.! This upcoming week, (June 22 – 26) will begin the framing process for the N. 10th St. sidewalk between Ferry and Main Streets. During this work, crews will also be installing the brick paver base sections and tree grate frames.