Happy first full week of summer! Work continues on Main Street 5th-6th streets block. Crews are finishing up demo and removals, as well as completing sewer work. This week 5th -6th Southside curb and sidewalk work will begin, as well as work on light pole bases. Late in the week, installation of sidewalks, paver bands and tree grates will begin. More finishing touches will be added this week to Phase 2: 4th-5th Street Northside and 5th Street North of Main; with the installation of benches and trash cans.