Weekly Update 7/14/20
Along N. 10th St., progress continues for Phase 3 of the Streetscapes project. The curb and gutters, along with their tie-ins have had their concrete poured. Concrete for the alley approaches and sidewalks on N. 10th St. has been poured as well! This coming week, (July 13th – July 17th) will include the completion of the sidewalks! Work will continue with the pouring of concrete for the ramps followed by the installation of Tuftile ADA radial plates.