Weekly Update 7/21/20

Great progress is worth celebrating as concrete crews finished the curb and gutter tie-ins on N. 10th Street as part of Phase 3 of the Streetscapes project for Downtown Lafayette! Concrete work continued with the pouring of alley approaches and sidewalks, concrete ramps and TriStop systems to prevent tripping hazards, and paver sections along N. 10th Street. This week, (July 20th – 24th) please be aware that crews will be shutting down Eastbound traffic on Main Street, from the 11th St. cross street to 9th St., as construction moves from N. 10th Street onto Main Street. This transition will result in the removal of old sidewalk on Main Street, and the installation of temporary access points for businesses and residents on Main Street.