Weekly Update 8/4/20
Begun last week (July 27th – July 31st) for Phase 3 of the Streetscapes project for Downtown Lafayette, was the removal of sidewalk along Main Street followed by the installation of temporary access points for business and residents. This was paired with the installation of storm underdrains, completion of construction of a modular block walls in coal chutes along Main St. between 11th and 10th Streets. On 10th St., decorative brick pavers have begun to be installed! This upcoming week, (August 3rd – August 7th) will see the electric conduit being switched over, and the decorative brick paver work continuing. Then, the framing process for the curb and gutter on Main St. between N. 10th St. and 11th St. will begin!